PROJECT PLANNING &
PROJECT MANAGEMENT
INTEGRATING MICROSOFT PROJECT, RISK MANAGEMENT &
COST CONTROL IN A MECHANICAL REFIT PROJECT
KAMARUL EFFENDI • 07/10/2026
COURSE OVERVIEW & LEARNING
OBJECTIVES
Master project planning techniques
Use MicrosoftProject to build & track schedules
Apply risk management throughout the project lifecycle
Implement cost-control measures & Earned Value Management
AGENDA (30MIN)
1. Introduction
2. Project Lifecycle & Phases
3. MicrosoftProject Basics
4. Plant Mechanical Refit – Project Charter
5. Work Breakdown Structure (WBS)
6. Scheduling & Network Diagram
7. Risk Management Process
8. Cost Control & Earned Value
9. Q&A / Wrap-up
PROJECT LIFECYCLE & PHASES
Initiation → Planning → Execution → Monitoring & Control → Closing
Plant refit specifics: shutdown window, safety, maintenance integration
MICROSOFTPROJECT – OVERVIEW
Desktop vs. Web version
Key features: Gantt, Resource Sheet, Tracking, Baseline
Integration with Excel & Teams
PROJECT CHARTER – PLANT
MECHANICAL REFIT
Purpose: Upgrade piping & boiler system for 20% uptime increase
Scope: Remove & replace 15% of plant piping, retrofit control panel
Stakeholders: Operations, Maintenance, Safety, Finance
Success Criteria: ≤5% cost variance, 95% uptime post-refit
WORK BREAKDOWN STRUCTURE
(WBS)
1.0 Project
Management
Project Plan
1.1 Planning Schedule & Budget
1.2 Execution Refit Work
1.3 Monitoring Status Reports
1.4 Closing Final Handover
SCHEDULE DEVELOPMENT – KEY STEPS
Define activities & durations (PERT)
Identify dependencies (Finish-to-Start, etc.)
Assign & level resources
Include shutdown window constraints
NETWORK DIAGRAM & CRITICAL PATH
Create swim-lane diagram (swim-lane layout)
Highlight critical path activities
Calculate float for non-critical tasks
MICROSOFTPROJECT – BUILDING THE
SCHEDULE
Create new project → Enter tasks
Set durations & dependencies
Assign resources → Level if needed
Review Gantt chart for critical path
BASELINE CREATION & TRACKING
Create baseline (Plan → Set Baseline)
Track progress: Actual Start/Finish, Variance
Use Tracking Gantt view for visual comparison
RISK MANAGEMENT – OVERVIEW
Risk vs. Issue definition
Process: Identify → Analyze → Plan → Monitor
Tools: Risk Register, Probability/Impact Matrix
RISK IDENTIFICATION – PLANT REFIT
R-001 Mechanical
failure during
shutdown
0.30 $400k Engineering
Lead
R-002 Supply chain
delay for
piping
0.45 $200k Procurement
Manager
R-003 Regulatory
compliance
change
0.20 $150k Compliance
Officer
R-004 Workforce
skill gaps
0.35 $80k HR Manager
RISK ANALYSIS – QUANTITATIVE &
QUALITATIVE
Probability × Impact scoring
Qualitative categories: Low / Medium / High
Example: 0.4 × $200k = $80k risk exposure
RISK RESPONSE PLANNING
Avoid, Mitigate, Transfer, Accept
Action plans with owners & timelines
Integrate contingency tasks into MS Project
RISK MONITORING & REPORTING
Weekly risk review meetings
Dashboard (PowerBI/Excel) heat map
Trigger thresholds (e.g., >10% of exposure)
COST CONTROL – BUDGETING
BASICS
Cost Baseline: labor, materials, equipment, overhead
Use MS Project’s Cost Sheet & Cost per Resource
EARNED VALUE MANAGEMENT (EVM)
– KEY METRICS
PV (Planned Value) Budgeted Cost of
Planned Work
Baseline cost
EV (Earned Value) Budgeted Cost of
Completed Work
Actual value of work
done
AC (Actual Cost) Sum of Actual Costs to
date
Cost incurred
ΔE = EV-PV
Variance in schedule
Positive → Ahead of plan
ΔC = AC-PV
Cost variance
Negative → Under
budget
CPI = EV/AC Cost Performance Index
>1→cost efficient
SPI = EV/PV Schedule Performance
Index
>1→ahead of
schedule
EVM IN MS PROJECT – DEMO
Set up Cost column & enter actuals
Use Task Usage view to input AC
Generate EVM report (Project → Reports → Earned Value)
CONTINGENCY & RESERVE
MANAGEMENT
Separate contingency funds for unplanned events
Reserve for schedule (management reserve)
Track via MS Project’s Contingency Cost field
COST-CONTROL MEASURES –
PRACTICAL TIPS
Regular cost-forecast updates
Standardized procurement contracts
Early warning of scope creep
Lean maintenance principles (5S, Kaizen)
INTEGRATED PROJECT DASHBOARD
Combined view: Schedule (Gantt), Cost (EVM), Risk (Heat Map)
Real-time data from MS Project to PowerBI
Example dashboard screenshot
LESSONS LEARNED – CASE STUDY
(PLANT REFIT)
What worked: Early risk identification, proactive resource leveling
What didn’t: Underestimation of safety downtime, insufficient
contingency buffers
Take-aways for future projects
Q & A
SUMMARY & KEY TAKE-AWAYS
Build a robust WBS & schedule in MS Project
Embed risk & cost control from day1
Use EVM and dashboards for proactive management
RESOURCES & FURTHER READING
PMBOK® Guide – 7th Edition
Microsoft Project help: Learn & Tutorials
Risk Register Templates (Excel)
Cost-control frameworks (Six Sigma, Lean)
THANK YOU